en
CASE
CASE

Can You Re-Seal Curtain Wall Without Scaffolding?

Short answer: can you re-seal a curtain wall from a scissor lift?

Yes, for curtain wall sealant access over the lower eight to twelve metres of a flat facade, and only if three conditions hold: the ground in front of the building can take 500 kPa without marking, the work face is within reach of the platform without extending over a projection, and the building can accept a machine standing on its forecourt for the duration. When any of those three fails, scaffolding is the right answer and a scissor lift is not.

The constraint is not the height

Most of the discussion about a scissor lift for curtain wall work focuses on height. Height is the easy part to answer: a 9.8 m platform with a person standing on it puts the working hands at roughly 11.5 m, which covers the first three floors of a typical commercial building. The GTJZ-1416 at 13.8 m covers four to five.

The constraint that actually stops projects is the ground. A 2,550 kg machine on four solid tyres standing on a paved forecourt applies about 500 kPa per wheel, and more when the platform is loaded and the deck is out. Polished granite paving laid on a sand bed will not take that without visible damage. Neither will asphalt in a heatwave. We have seen a facade job stopped on day two because the client's own paving contractor refused to sign off on the marks.

GTJZ-1012 platform level with a curtain wall during sealant replacement

The platform sits parallel to the glass for the whole pass. That is the reason sealant work suits a scissor rather than a boom.

What scaffolding actually costs, in area and days

Stuck on this step?

Send the site details — an engineer answers within one business day.

Scaffolding is not expensive because of the hire charge. It is expensive because of the footprint. A five-storey independent scaffold with a 1.2 m working lift and debris netting occupies a strip about 2.4 m wide along the elevation, plus a 0.6 m safety zone. On a 30 m elevation that is 90 m² of forecourt closed for the duration, and the duration is two weeks for erection, work and striking.

ItemScaffolding, 30 m elevation, 3 floorsScissor lift, same elevation
Ground occupied~90 m² closed for 2 weeks~6 m² of working position, moved as work progresses
Set-up time2-3 days erection, 1 day strikeNone; machine arrives on a trailer
Access to retail entranceUsually blocked or reducedMaintained, if the route is planned
Work rate, sealantContinuous face, but fixed once builtLimited by repositioning, not by the platform
Ground protection neededBase plates on spreadersPlate under each wheel, or a load-spreading mat

Choosing a scaffolding alternative is not about which is faster. It is about whether the building can afford to lose its frontage for two weeks. On a trading retail unit, that single point usually decides the method on its own.

Making it work on a real facade

Plan the passes, not the days. A scissor lift for curtain wall re-sealing works one vertical strip at a time. Mark the elevation in 2.27 m widths, which is the platform length on the 1012, and treat each strip as a separate task. A two-person crew sealing joints does roughly one strip per hour on a clean facade, so a 30 m elevation is 13 passes, or about two working days including moving and set-up.

Keep the platform close. Scissor lift facade work needs the operator within about 300 mm of the joint. The machine has to sit parallel, which means the ground in front of the facade has to be clear of planters, bollards and steps for the whole length. Walk the elevation with a tape before you commit.

Use the deck, not the guardrail. The extension deck extends the usable floor by 900 mm on the 1012, which is what lets the operator reach past a mullion without leaning over the rail. Leaning over the rail is the thing that turns a routine job into an incident, and it happens on every facade job where the deck was left retracted to save time.

Where a scissor lift cannot do the job

  • Above 12 m of work face. Not because the machine cannot reach, but because the ground-level footprint and the wind exposure start to work against a vertical-only platform. Above that, use a boom or a suspended platform.
  • Projections. Balconies, brise-soleil, projecting cornices or a stepped facade stop the platform getting within reach. A scissor lift cannot work around an obstruction; it can only go up and down in front of it.
  • Fragile or finished paving. If the client will not accept plates or mats on the surface, the machine cannot stand there. This is a commercial constraint, not an engineering one, and it kills more jobs than any technical limit.
  • Sloping forecourts. Above 10% grade on a paved surface, repositioning becomes slow and the platform level is compromised. Many retail forecourts fall away towards drainage and are steeper than they look.

What we ask before quoting a facade job

For scissor lift building maintenance we ask three questions: what is the highest joint to be sealed, what is the ground surface in front of the elevation, and can the forecourt be closed to vehicles for the duration. With those answers we can say whether a GTJZ-1012 or the taller GTJZ-1416 is the right unit, or whether we should tell you to keep the scaffold.

One detail from our own dispatch

On facade enquiries we ask for a photograph of the ground, not of the building. The building tells us the height, which we can read from the drawing. The ground tells us whether the job is possible, and it is the one thing customers rarely send. Send both through the contact form and the answer is usually back the same day.

Same problem on your site?

Tell us the constraint you are stuck on — floor loading, doorway width, cold store, aisle width, charge window. We will tell you which model works, what it costs, and what we would refuse to sell you.

Verification code
Chat on WhatsApp

Engineer reply within one business day (Mon–Sat, GMT+8).

Related Products
Read More >>
GTJZ-1416 45ft (13.8 m) Scissor Lift, No Outriggers — 230 kg GTJZ-1416 45ft (13.8 m) Scissor Lift, No Outriggers — 230 kg
10-26,2026
45ft (13.8m) electric scissor lift with no outriggers: 230kg load, 15.8m working height, 1,400mm width. CE / EN 280, fac...
GTJZ-1012 32ft (9.8 m) Self-Propelled Scissor Lift — 320 kg GTJZ-1012 32ft (9.8 m) Self-Propelled Scissor Lift — 320 kg
10-26,2026
32ft (9.8m) electric scissor lift: 320kg load, 11.8m working height, 1,160mm width, 4x2 drive and 900mm extension deck. ...